Back to Forecasting
BVNActive

Will BVN's San Gabriel produce less than 48,055 oz gold in FY2026?

Resolves March 15, 2027(352d)
IG: 0.64

Current Prediction

47%
Likely No
Model Agreement92%
Predictions9 runs
Last UpdatedMarch 27, 2026

Why This Question Matters

The 48,055 oz target is already a 30-50% cut from original 70,000-90,000 oz guidance due to the December 2025 accident. Missing even this reduced target would confirm that San Gabriel execution is systematically challenged — not a one-time event — and would strengthen the case that the $720-750M CapEx project is delivering below-plan returns. Meeting the target would validate the accident as a contained incident.

CAPITAL_DEPLOYMENTREVENUE_DURABILITY

Prediction Distribution

0%25%50%75%100%
opus
sonnet
haiku
Range: 42%55%Aggregate: 47%
Individual Predictions(9 runs)
opusRun 1
45%

The 48,055 oz target is already a significantly reduced figure (cut 30-50% from original 70,000-90,000 oz). Management should have baked in the accident impact when setting this revised target. However, BVN has a documented pattern of over-promising on San Gabriel: CapEx overruns (7 layers of grouting vs 2-3 designed), quarry inadequacy, and now a production-limiting accident. A new mine ramping up after a major accident, with pending water license and ventilation restrictions (3 of 6 mining levels), faces considerable execution risk. The target requires averaging roughly 4,000 oz/month — achievable at 2,000 tpd if grades hold, but ramp-up curves are typically choppy.

Already-reduced target should incorporate known issuesSystematic pattern of execution challenges at San GabrielRamp-up curves typically have more friction than projected
opusRun 2
52%

The water license remains pending — without it, water management for processing may be constrained. The ventilation redesign restricts mining to half the planned levels. New mines consistently face unexpected issues in their first full year of production. BVN has failed to execute San Gabriel on every previous milestone: CapEx budget, construction timeline, and now production targets. While the 48,055 oz figure is already reduced, I believe the pattern suggests even this conservative target may prove optimistic. The combination of pending permit, restricted mining levels, and first-year ramp-up friction creates a realistic path to missing even the low-end target.

Pending water license may constrain processingEvery prior San Gabriel milestone has been missed or revisedFirst-year ramp-up friction at new mines is common
opusRun 3
42%

Counterarguments to a miss: (1) Management set 48,055 oz AFTER knowing about the accident, so this figure should incorporate realistic constraints. (2) At current gold prices ($4,500/oz), there is enormous financial incentive to maximize output — management will prioritize San Gabriel operations. (3) The mine has already produced first dore in December 2025, so it is not starting from zero. (4) 2,000 tpd at reasonable gold grades should be achievable with only 3 mining levels. Against: water license uncertainty and BVN's track record of over-promising. I lean slightly toward meeting the target given it was set post-accident.

Target was set after the accident — already incorporates known issuesEnormous financial incentive at $4,500 goldFirst dore already produced — not starting from zero
sonnetRun 1
48%

Coin-flip territory. The target is already reduced, which argues for achievability. But BVN has a terrible track record on San Gabriel milestones. The water license is still pending, and new mines always face unexpected issues. I lean very slightly toward meeting the target because management set it with full knowledge of the accident, but it is genuinely uncertain.

Reduced target argues for achievabilityBVN track record argues againstNear coin-flip
sonnetRun 2
55%

I weigh the execution history heavily. BVN has systematically over-promised and under-delivered on San Gabriel at every stage. The water dam required 7 layers of grouting instead of 2-3. The quarry material was inadequate. The accident cut production targets by 30-50%. This pattern suggests the remaining uncertainties (water license, ventilation constraints, ramp-up friction) are more likely to resolve unfavorably than favorably. Even with the reduced target, I put the probability of a miss at slightly above 50%.

Systematic over-promising and under-delivery patternWater license uncertainty adds riskRemaining uncertainties likely to resolve unfavorably given track record
sonnetRun 3
43%

The question is whether a production miss at an already-reduced target signals systemic problems. I note that the 48,055 oz figure is a FY2026 target, meaning production has the full year to ramp up. Even if Q1 is slow due to water license delays, strong Q3-Q4 production could compensate. At $4,500 gold, every ounce produced is worth nearly $4,500, so management will push hard. I lean slightly toward meeting the reduced target.

Full year allows for back-loaded ramp-upStrong Q3-Q4 could compensate for slow Q1$4,500/oz gold provides maximum operational incentive
haikuRun 1
47%

Target already reduced post-accident. BVN has a pattern of missing milestones, but management set this figure knowing the constraints. Water license is a wildcard. Near coin-flip leaning slightly toward meeting target.

Post-accident target already conservativeBVN execution track record is poorWater license adds uncertainty
haikuRun 2
50%

Genuinely uncertain. Pattern of misses vs already-reduced target. Water license pending. New mine ramp-up risk. High gold price provides incentive. Setting at 50% — true coin flip.

Pattern of missesReduced targetGenuine uncertainty
haikuRun 3
44%

Management is highly incentivized to hit this target — it is already embarrassingly low compared to original guidance. At $4,500 gold, they will pull every lever. The accident impact is already baked in. Slightly more likely to meet than miss.

Management reputational incentive to hit reduced target$4,500 gold maximizes operational focusAccident impact already incorporated

Resolution Criteria

Resolves YES if BVN reports San Gabriel FY2026 gold production below 48,055 oz in its full-year production report or 20-F filing. Resolves NO if production meets or exceeds 48,055 oz.

Resolution Source

BVN FY2026 production report or 20-F filing

Source Trigger

San Gabriel water license issuance and 2026 production ramp-up vs 48,055 oz guidance

stress-scannerCAPITAL_DEPLOYMENTHIGH
View BVN Analysis

Full multi-lens equity analysis