Back to Forecasting
AESActive

Will AES complete at least 2 GW of new renewables capacity in H1 2026?

Resolves October 31, 2026(224d)
IG: 0.48

Current Prediction

68%
Likely Yes
Model Agreement96%
Predictions9 runs
Last UpdatedMarch 20, 2026

Why This Question Matters

Backlog execution pace directly validates the REVENUE_DURABILITY assessment. The Gravy Gauge conditioned its assessment on successful execution of the 11.1 GW backlog. If H1 2026 completions reach 2 GW, the execution engine is on track; shortfalls would raise questions about construction delays, supply chain issues, or interconnection bottlenecks.

REVENUE_DURABILITYCOMPETITIVE_POSITION

Prediction Distribution

0%25%50%75%100%
opus
sonnet
haiku
Range: 65%72%Aggregate: 68%
Individual Predictions(9 runs)
opusRun 1
72%

AES completed 2.9 GW in the first 3 quarters of 2025, implying a run rate of ~1 GW per quarter. Sustaining this pace through H1 2026 (Q1 + Q2) would deliver 2 GW. The 4.8 GW under construction as of Q3 2025 provides ample pipeline for near-term completions. However, construction and interconnection timelines can be lumpy — some quarters deliver more than 1 GW, others less. The take-private deal announcement may not directly affect construction but could affect contractor priority or utility interconnection processes. Domestic supply chain advantage mitigates supply disruption risk. 72%.

~1 GW per quarter run rate in 2025 supports 2 GW in H1 20264.8 GW under construction provides ample pipelineInterconnection queue delays are the primary risk to completions
opusRun 2
68%

The 2 GW threshold for a half-year is achievable given the run rate, but renewables construction has seasonal patterns — Q1 may be slower due to winter weather in some geographies, and Q2 ramps up. The data center backlog projects (nearly half of 4 GW under construction completing in next 18 months from Q3 2025 = by Q1 2027) should provide steady completions. But 'completing in next 18 months' doesn't mean they all complete in H1 2026 — completions will be spread across 6 quarters. I weight at 68%, reflecting the achievable run rate with a discount for lumpiness and seasonal patterns.

Seasonal construction patterns may reduce Q1 completionsData center backlog spread across 6 quarters, not concentrated in H1 2026Rolling construction programs support steady but not guaranteed pace
opusRun 3
70%

The committee's monitoring trigger set the threshold at <0.5 GW per quarter as signaling a slowdown. For H1 2026 (2 quarters), 2 GW requires 1 GW per quarter — double the 'slowdown signal' threshold but matching the 2025 run rate. The favorable contractor arrangements (rolling construction programs) and domestic supply chain reduce execution risk. Interconnection queue delays are the primary bottleneck, and these are hard to predict. 70% reflects the strong pipeline with residual interconnection risk.

1 GW/quarter required matches 2025 run rate exactlyRolling construction programs support consistent executionInterconnection queue delays are hard to predict
sonnetRun 1
67%

The run rate supports this, but H1 2026 completions depend on projects that are currently in late-stage construction. Interconnection agreements, grid upgrades, and final commissioning can delay commercial operation dates by weeks or months. The 2 GW threshold is achievable but not as comfortable as it might seem from the run rate alone. Projects slip between quarters routinely. 67%.

Late-stage construction delays are commonInterconnection agreements can delay commercial operation2 GW is achievable but projects routinely slip between quarters
sonnetRun 2
65%

I weigh interconnection risk more heavily. Grid interconnection queues nationally have become a major bottleneck for renewables. Even with a strong construction pipeline, the final step — connecting to the grid — is controlled by utilities and ISOs with their own timelines. AES's own utility operations in Indiana and Ohio may help for projects in those territories, but the 50 GW development pipeline suggests projects across many jurisdictions. 65%.

Grid interconnection queues are a national bottleneckFinal grid connection step controlled by external partiesMulti-jurisdiction project portfolio creates varied completion risk
sonnetRun 3
70%

The combination of strong pipeline (4.8 GW under construction), proven execution (2.9 GW completed in 2025), domestic supply chain advantage, and data center customer pull (hyperscalers want their contracted power online) supports achieving 2 GW in H1 2026. Hyperscaler customers add a pull factor — they're incentivized to help projects clear interconnection and permitting hurdles. 70%.

Hyperscaler customer pull accelerates project completionProven execution track record in 2025Domestic supply chain reduces supply disruption risk
haikuRun 1
70%

Strong pipeline and proven run rate support 2 GW. Interconnection risk and seasonal lumpiness are the main concerns. 70%.

Strong construction pipelineProven ~1 GW/quarter run rateInterconnection risk moderates confidence
haikuRun 2
66%

Achievable but not certain. Construction and interconnection timing is inherently uncertain. The 2 GW threshold for 2 quarters is reasonable given the pipeline but projects slip routinely. 66%.

Reasonable threshold given pipelineConstruction timing inherently uncertainProjects slip between quarters routinely
haikuRun 3
68%

The run rate and pipeline both support this. Domestic supply chain and rolling construction programs reduce risk. Interconnection queues are the wildcard. 68%.

Run rate and pipeline support targetDomestic supply chain reduces supply riskInterconnection queues are the wildcard

Resolution Criteria

Resolves YES if AES reports cumulative H1 2026 renewables capacity completions (new GW online) of 2.0 GW or more. Resolves NO if completions are below 2.0 GW.

Resolution Source

AES Q1 2026 and Q2 2026 earnings releases

Source Trigger

Track GW completion rate vs. schedule. Any quarter with <0.5 GW completions signals construction slowdown.

gravy-gaugeREVENUE_DURABILITYHIGH
View AES Analysis

Full multi-lens equity analysis