Will Greenstone produce less than 110,000 oz in H1 2026?
Current Prediction
Why This Question Matters
Greenstone is EQX's largest single asset and its ramp-up trajectory is the most direct test of execution capability. The Gravy Gauge debate on whether 700,000-800,000 oz guidance is conservative or aspirational converged on 'moderately conservative' based on improving throughput metrics. If H1 production falls below 110,000 oz, it invalidates the ramp-up progress narrative and raises the risk that full-year guidance will be missed.
Prediction Distribution
Individual Predictions(9 runs)
The question asks if Greenstone will produce LESS than 110,000 oz in H1 2026 — a downside scenario. Annual guidance is 250,000-300,000 oz, so H1 production of 110,000 oz would be only 40% of the midpoint. Greenstone has shown consistent ramp-up improvement: 17% → 28% → 36% → 50% of days above nameplate. At 50% of days above nameplate in Q1 2026 and improving trend, quarterly production should be running at 55,000-70,000 oz range. Two quarters at that rate would yield 110,000-140,000 oz in H1. The question is whether Q1 was weaker (early ramp-up) and Q2 catches up. The improving throughput trajectory strongly suggests 110,000 oz is achievable.
110,000 oz in H1 represents ~60-65 oz/day over ~180 days, which is well within capability for a mine ramping to 300,000 oz/yr nameplate. The arsenic-grade relationship flagged in the dossier could reduce recoveries at higher grades, which is a risk factor. However, even at reduced recovery rates, the throughput improvements (50% of days above nameplate) suggest production should comfortably exceed 110,000 oz in H1. The main risk would be an extended unplanned shutdown — equipment failure, environmental incident, or labor disruption — which is a low probability but non-zero risk.
The H1 2026 period partially overlaps with the data we already have — Q1 2026 throughput data shows 50% of days above nameplate, which is the best quarter yet. Even if Q1 production was slightly below the half-year run rate needed, Q2 should more than compensate given the improving trajectory. The 110,000 oz threshold is intentionally set as a warning level, not a base case expectation. Falling below it would require a significant operational setback that the committee did not identify as probable.
Greenstone's ramp-up trajectory is clearly positive. 50% of days above nameplate in Q1 2026 means the mine is running well above the threshold needed to produce 110,000 oz in a half year. This is a relatively easy bar to clear unless something goes materially wrong. The only scenarios where production falls this short are an extended shutdown or a previously unidentified metallurgical problem.
While the trajectory is positive, ramp-ups are inherently uncertain. The 50% of days above nameplate means 50% of days were BELOW nameplate — there's still significant variability. The arsenic-grade relationship creates a headwind on higher grades. I weight ramp-up uncertainty slightly higher than other models — mines in ramp-up can have setbacks. But 110,000 oz is still a low threshold given the improving data, so probability of missing remains below 20%.
The data supports continued improvement at Greenstone. From 17% to 50% of days above nameplate over 12 months is genuine operational progress. At this trajectory, Q2 should be even better than Q1. Missing 110,000 oz would represent a meaningful regression from the established trend, which while possible is unlikely without a specific identified cause. No such cause was flagged by the committee.
Greenstone ramping well — 50% days above nameplate in Q1 2026. 110,000 oz in H1 is a low threshold for a 300K/yr mine. Should easily exceed unless major setback. Low probability of missing.
Ramp-ups carry inherent risk. Arsenic-grade issue could limit production. But improving trajectory from 17% to 50% above nameplate makes sub-110K unlikely. Slightly higher than minimum to account for ramp-up uncertainty.
At 50% of days above nameplate in Q1 and improving, Greenstone should produce well above 110,000 oz in H1 2026. This is a downside threshold designed to flag problems, not a likely outcome. Very low probability.
Resolution Criteria
Resolves YES if EQX's H1 2026 production report or Q2 2026 earnings disclosure shows Greenstone produced fewer than 110,000 oz in the first half of 2026.
Resolution Source
EQX Q2 2026 earnings release or H1 2026 production report
Source Trigger
Greenstone H1 2026 production below 110,000 oz would indicate ramp-up thesis is at risk
Full multi-lens equity analysis