Back to Forecasting
EQXActive

Will Greenstone produce less than 110,000 oz in H1 2026?

Resolves August 15, 2026(146d)
IG: 0.60

Current Prediction

15%
Likely No
Model Agreement94%
Predictions9 runs
Last UpdatedMarch 21, 2026

Why This Question Matters

Greenstone is EQX's largest single asset and its ramp-up trajectory is the most direct test of execution capability. The Gravy Gauge debate on whether 700,000-800,000 oz guidance is conservative or aspirational converged on 'moderately conservative' based on improving throughput metrics. If H1 production falls below 110,000 oz, it invalidates the ramp-up progress narrative and raises the risk that full-year guidance will be missed.

REVENUE_DURABILITY

Prediction Distribution

0%25%50%75%100%
opus
sonnet
haiku
Range: 11%20%Aggregate: 15%
Individual Predictions(9 runs)
opusRun 1
15%

The question asks if Greenstone will produce LESS than 110,000 oz in H1 2026 — a downside scenario. Annual guidance is 250,000-300,000 oz, so H1 production of 110,000 oz would be only 40% of the midpoint. Greenstone has shown consistent ramp-up improvement: 17% → 28% → 36% → 50% of days above nameplate. At 50% of days above nameplate in Q1 2026 and improving trend, quarterly production should be running at 55,000-70,000 oz range. Two quarters at that rate would yield 110,000-140,000 oz in H1. The question is whether Q1 was weaker (early ramp-up) and Q2 catches up. The improving throughput trajectory strongly suggests 110,000 oz is achievable.

Consistent ramp-up improvement from 17% to 50% of days above nameplate110,000 oz is only 40% of annual midpoint — a low barQ2 2026 should be better than Q1 given improving trajectory
opusRun 2
18%

110,000 oz in H1 represents ~60-65 oz/day over ~180 days, which is well within capability for a mine ramping to 300,000 oz/yr nameplate. The arsenic-grade relationship flagged in the dossier could reduce recoveries at higher grades, which is a risk factor. However, even at reduced recovery rates, the throughput improvements (50% of days above nameplate) suggest production should comfortably exceed 110,000 oz in H1. The main risk would be an extended unplanned shutdown — equipment failure, environmental incident, or labor disruption — which is a low probability but non-zero risk.

110,000 oz threshold is relatively low for a 300K/yr nameplate mineArsenic-grade relationship could limit recovery ratesUnplanned shutdown is the main risk to missing this threshold
opusRun 3
12%

The H1 2026 period partially overlaps with the data we already have — Q1 2026 throughput data shows 50% of days above nameplate, which is the best quarter yet. Even if Q1 production was slightly below the half-year run rate needed, Q2 should more than compensate given the improving trajectory. The 110,000 oz threshold is intentionally set as a warning level, not a base case expectation. Falling below it would require a significant operational setback that the committee did not identify as probable.

Q1 2026 data already shows best throughput quarter110,000 oz is a warning threshold, not base caseWould require significant operational setback to miss
sonnetRun 1
14%

Greenstone's ramp-up trajectory is clearly positive. 50% of days above nameplate in Q1 2026 means the mine is running well above the threshold needed to produce 110,000 oz in a half year. This is a relatively easy bar to clear unless something goes materially wrong. The only scenarios where production falls this short are an extended shutdown or a previously unidentified metallurgical problem.

Clear positive ramp-up trajectoryBar is relatively easy to clear at current throughputWould require extended shutdown to miss
sonnetRun 2
20%

While the trajectory is positive, ramp-ups are inherently uncertain. The 50% of days above nameplate means 50% of days were BELOW nameplate — there's still significant variability. The arsenic-grade relationship creates a headwind on higher grades. I weight ramp-up uncertainty slightly higher than other models — mines in ramp-up can have setbacks. But 110,000 oz is still a low threshold given the improving data, so probability of missing remains below 20%.

50% below nameplate days indicates remaining variabilityArsenic-grade headwind on high gradesRamp-up mines can have unexpected setbacks
sonnetRun 3
16%

The data supports continued improvement at Greenstone. From 17% to 50% of days above nameplate over 12 months is genuine operational progress. At this trajectory, Q2 should be even better than Q1. Missing 110,000 oz would represent a meaningful regression from the established trend, which while possible is unlikely without a specific identified cause. No such cause was flagged by the committee.

12-month improving trend from 17% to 50%Q2 should be better than Q1 on trendNo specific regression risks identified by committee
haikuRun 1
13%

Greenstone ramping well — 50% days above nameplate in Q1 2026. 110,000 oz in H1 is a low threshold for a 300K/yr mine. Should easily exceed unless major setback. Low probability of missing.

Strong ramp-up trajectoryLow threshold relative to nameplateNo major setback risks identified
haikuRun 2
17%

Ramp-ups carry inherent risk. Arsenic-grade issue could limit production. But improving trajectory from 17% to 50% above nameplate makes sub-110K unlikely. Slightly higher than minimum to account for ramp-up uncertainty.

Ramp-up inherent riskArsenic-grade recovery limitationStrong improving throughput trend
haikuRun 3
11%

At 50% of days above nameplate in Q1 and improving, Greenstone should produce well above 110,000 oz in H1 2026. This is a downside threshold designed to flag problems, not a likely outcome. Very low probability.

Designed as a warning thresholdCurrent throughput well above needed rateImproving trend supports confidence

Resolution Criteria

Resolves YES if EQX's H1 2026 production report or Q2 2026 earnings disclosure shows Greenstone produced fewer than 110,000 oz in the first half of 2026.

Resolution Source

EQX Q2 2026 earnings release or H1 2026 production report

Source Trigger

Greenstone H1 2026 production below 110,000 oz would indicate ramp-up thesis is at risk

gravy-gaugeREVENUE_DURABILITYHIGH
View EQX Analysis

Full multi-lens equity analysis