Back to Forecasting
SCCOActive

Will Tia Maria reach 50% construction completion by year-end 2026?

Resolves February 28, 2027(344d)
IG: 0.80

Current Prediction

50%
Likely No
Model Agreement94%
Predictions9 runs
Last UpdatedMarch 20, 2026

Why This Question Matters

Tia Maria is the only active growth project in the $20.5B program. Reaching 50% completion would be the first tangible evidence that the growth pipeline can deliver, de-escalating REGULATORY_EXPOSURE and partially validating the premium valuation. Failure to reach 50% would compound concerns about the capex program's feasibility.

REGULATORY_EXPOSURECAPITAL_DEPLOYMENT

Prediction Distribution

0%25%50%75%100%
opus
sonnet
haiku
Range: 46%55%Aggregate: 50%
Individual Predictions(9 runs)
opusRun 1
55%

Tia Maria is at 24% completion with 9-10 months until year-end 2026. Reaching 50% requires 26 additional percentage points — approximately 2.6-2.9% per month. At 24% with $800M of $1.8B committed (44% of budget spent for 24% completion), the spending-to-progress ratio suggests slower-than-linear progress in the early phases (site preparation, foundation work). Construction typically accelerates in mid-phases as concurrent work streams multiply. The H2 2027 commissioning target implies management expects rapid progress through 2026-2027. However, community protest risk is unquantified and Tia Maria's history includes multiple prior suspensions.

26pp needed in 9-10 months (~2.7pp/month) is achievable paceConstruction accelerates in mid-phasesCommunity protest risk is unquantified wild card
opusRun 2
50%

The math is straightforward but the uncertainty is high. From 24% to 50% is a 26pp increase needed in ~9 months. Large mining construction projects frequently experience delays — schedule overruns of 20-50% are common in the industry. The $800M spent for 24% completion implies a cost-to-progress curve that may flatten as the project moves into equipment installation and commissioning preparation phases. The decade-long permitting history demonstrates the project operates in a hostile social environment. No data on current community sentiment or protest activity. Low confidence due to high uncertainty on both construction pace and social disruption risk.

Mining construction frequently overruns schedulesBudget curve suggests non-linear progressNo community sentiment data available
opusRun 3
52%

Management's H2 2027 commissioning target implies they expect 80%+ completion by year-end 2026. If the commissioning timeline is realistic, reaching 50% by year-end 2026 is well within the implied construction curve. However, management's growth timelines for SCCO have historically been optimistic — Los Chancas has been in development indefinitely, and Tia Maria itself took 10+ years to reach construction. The key question is whether management's construction timeline is more reliable than their development timelines. Once construction begins, engineering execution is more predictable than regulatory/social outcomes. Modest lean toward YES.

H2 2027 commissioning implies >50% by year-end 2026Construction execution more predictable than permittingHistorical timeline optimism is a concern
sonnetRun 1
48%

24% to 50% in 9 months is aggressive for a greenfield mining project. Budget spent ($800M of $1.8B = 44%) exceeds physical progress (24%), suggesting either front-loaded costs or cost overruns already emerging. Mining megaprojects commonly miss schedule milestones by 6-18 months. The protest risk is material but unquantifiable. If construction proceeds uninterrupted, 50% is achievable by year-end. If any disruption occurs — protest, supply chain, labor — the tight timeline has no slack. Near coin-flip with slight lean toward NO.

Budget spent (44%) exceeds physical progress (24%)Tight timeline with no slack for disruptionsMining megaproject schedule overruns common
sonnetRun 2
53%

The H2 2027 commissioning target is the strongest evidence for reaching 50% by year-end 2026. For commissioning to be feasible, the project must be substantially complete (>70%) by mid-2027, implying 50%+ well before year-end 2026. Management has $800M committed and active construction underway. The risks (protests, supply chain) are real but there's no current evidence of disruption. Construction is advancing from 24% and the permitting hurdles that caused the decade-long delay are now cleared. Slight lean toward YES based on implied construction curve.

H2 2027 commissioning requires rapid progressPermitting hurdles now clearedNo current evidence of disruption
sonnetRun 3
46%

High uncertainty makes this close to a coin-flip. On one hand, management targets H2 2027 commissioning, implying rapid construction through 2026. On the other hand, the budget-to-progress ratio (44% spent for 24% complete) suggests the project may already be behind schedule or over budget. Latin American mining construction has a poor track record on schedule adherence. Community protest risk is unquantifiable and could halt construction at any point. The decade of opposition hasn't disappeared — it has merely been managed through permits. Slight lean toward NO due to the budget-progress gap and historical overrun rates.

Budget-progress gap suggests schedule/cost issuesLatAm mining construction track record poorProtest risk unquantifiable
haikuRun 1
52%

24% to 50% in 9 months is ~2.9pp/month. Mining construction can achieve this pace when major earthworks and foundations are complete. H2 2027 commissioning target supports reaching 50% by year-end. Protest risk is the main downside. Slight lean YES.

Required pace achievable for mid-stage constructionH2 2027 target implies rapid progressProtest risk is key downside
haikuRun 2
47%

Mining megaproject schedule overruns are common (20-50% delays). Budget at 44% for 24% completion is a warning sign. But management has H2 2027 commissioning target. Near coin-flip with slight lean NO due to overrun base rates.

Megaproject overrun base ratesBudget-progress mismatchH2 2027 target supports some optimism
haikuRun 3
50%

True coin-flip. Arguments are balanced: H2 2027 commissioning target supports YES, but budget overrun signals and protest risk support NO. Insufficient data to break the tie. Low confidence reflects genuine uncertainty.

Balanced YES/NO factorsInsufficient data on community sentimentLow confidence appropriate

Resolution Criteria

Resolves YES if SCCO management reports Tia Maria construction at 50% or greater completion in the Q4 2026 earnings call or FY2026 10-K. Resolves NO if completion remains below 50% or construction is suspended.

Resolution Source

SCCO Q4 2026 earnings call transcript or FY2026 10-K

Source Trigger

Tia Maria reaches 50%+ construction completion on schedule

regulatory-readerREGULATORY_EXPOSUREHIGH
View SCCO Analysis

Full multi-lens equity analysis