Back to Forecasting
UAMYActive

Will UAMY complete first physical DLA contract delivery by June 30, 2026?

Resolves July 15, 2026(117d)
IG: 0.48

Current Prediction

72%
Likely Yes
Model Agreement81%
Predictions9 runs
Last UpdatedMarch 19, 2026

Why This Question Matters

The $248M DLA contract is the cornerstone of the revenue thesis (~$75M of $125M guidance). First physical delivery confirms transition from contractual commitment to operational execution. CEO says 'very close to delivering.'

REGULATORY_EXPOSURE

Prediction Distribution

0%25%50%75%100%
opus
sonnet
haiku
Range: 65%76%Aggregate: 72%
Individual Predictions(9 runs)
opusRun 1
75%

CEO Evans stated the first pallet is 'very close to delivering' as of March 19, and there are 465 tons of antimony inventory ($11.1M) available. The critical distinction is that initial DLA deliveries do NOT require Thompson Falls expansion — the existing smelter has been processing antimony from foreign sources throughout FY2025. The $248M contract has been upgraded (not downsized), indicating active engagement. China's antimony export restrictions create strategic urgency on both sides. The June 30 deadline provides 3.5 months from the 'very close' statement. Government sole-source contracts, once logistics are established, typically begin flowing. The Radersburg facility (military-spec processing) is described as 'next month or two' from operational, and if DLA requires mil-spec material, that facility needs to be ready — but this is a shorter timeline than Thompson Falls.

First pallet 'very close to delivering' — weeks not months465 tons inventory available for processing and deliveryExisting smelter capacity sufficient for initial deliveries
opusRun 2
68%

The inventory is available (465 tons) and existing capacity is operational. The question is whether DLA procurement bureaucracy, product specification compliance, and Radersburg facility readiness create delays beyond what 'very close' implies. Government contract deliveries involve quality assurance, testing, and documentation that can add weeks to months. First-time deliverers to DLA face a learning curve on compliance requirements. CEO Evans' use of 'very close' should be discounted somewhat given his promotional tendencies (same language pattern before Thompson Falls delays). However, the 3.5-month window to June 30 provides substantial buffer for bureaucratic delays.

Government procurement bureaucracy can add weeks to monthsFirst-time DLA deliverer faces compliance learning curve3.5-month window provides substantial buffer for delays
opusRun 3
72%

The DLA delivery question has fundamentally different risk characteristics than the Thompson Falls expansion. Thompson Falls required construction, supplier coordination, and weather-dependent work. DLA delivery requires product that already exists (465 tons of antimony inventory), processing through existing capacity, and logistics/paperwork. The execution barriers are lower and more within the company's control. The strategic urgency is mutual — DLA needs domestic antimony supply, and UAMY needs to demonstrate delivery capability. The $248M contract upgrade signals ongoing engagement. The main risk is if DLA requires specific product forms that need the Radersburg facility, which is 1-2 months from operational. Even with that dependency, June 30 is achievable.

Lower execution barriers than expansion projectsProduct exists in inventory — not waiting on constructionMutual strategic urgency between DLA and UAMY
sonnetRun 1
74%

This is the highest-probability market in this batch. The first pallet is described as imminent, inventory is on hand, existing processing capacity is available, and both parties (DLA and UAMY) have strong incentives to begin the delivery relationship. The June 30 deadline is generous for what CEO Evans describes as a near-term event. The only scenario where this resolves NO is if DLA product specifications require the Radersburg military-spec facility AND that facility is significantly delayed, or if unforeseen compliance/quality issues block delivery. Both are possible but unlikely to persist for 3.5 months.

Near-term event by management's own descriptionStrong dual-party incentive to begin deliveries3.5 months is generous for what's described as imminent
sonnetRun 2
65%

I discount the CEO's 'very close' language more than other models. Evans described Thompson Falls as imminent before multiple delays. Government contract first deliveries can face unexpected compliance hurdles — product testing, certification, documentation requirements that are new to a first-time supplier. The Radersburg military-spec facility being 'next month or two' from operational introduces a dependency if DLA requires processed-to-spec material (not just raw antimony). However, the 3.5-month window and the fact that DLA has actively upgraded the contract ($245M to $248M) suggest the relationship is moving forward. Probability is solidly above 50% but not as high as the surface-level 'very close' language suggests.

CEO 'very close' language has historically preceded delaysFirst-time supplier compliance hurdles are realRadersburg dependency if mil-spec processing required
sonnetRun 3
76%

The asymmetry of information here favors YES. The DLA contract has been in place for months, upgraded from $245M to $248M, and first delivery described as imminent. If there were fundamental blockers (product spec issues, compliance failures, quality problems), the contract would not have been upgraded. The DLA's strategic need for domestic antimony supply — with China's export ban since September 2024 — creates institutional urgency that commercial contracts lack. The 465-ton inventory provides immediate supply. June 30 is a comfortable timeline for an event described as weeks away. The residual NO probability comes from bureaucratic delays, not fundamental execution barriers.

Contract upgraded (not downsized) — no fundamental blockersDLA strategic urgency post-China export banResidual NO risk is bureaucratic, not fundamental
haikuRun 1
73%

First pallet 'very close' with 465 tons of inventory available. Existing processing capacity is operational. DLA contract upgraded to $248M showing active engagement. China export ban creates mutual urgency. June 30 provides 3.5 months of buffer. Strong YES lean.

Imminent first delivery with inventory on handContract upgraded showing active engagement3.5 months is generous buffer
haikuRun 2
70%

The DLA delivery has lower execution barriers than construction projects. Inventory exists, processing capacity is available, and the government has strategic urgency. The main risk is first-time supplier compliance and Radersburg military-spec facility readiness. 3.5 months provides ample buffer for these risks. Lean YES.

Lower execution barriers than expansionGovernment strategic urgencyCompliance and Radersburg are manageable risks
haikuRun 3
72%

CEO describes first delivery as imminent. Inventory is available. Contract has been upgraded. DLA needs domestic supply. June 30 provides adequate buffer. The only significant risk is first-time compliance issues with government delivery requirements, which could add weeks but not months. Lean YES.

Imminent delivery per CEOInventory and capacity availableGovernment compliance adds weeks not months

Resolution Criteria

Resolves YES if UAMY publicly confirms (via SEC filing, press release, or earnings call) that at least one physical delivery under the DLA sole-source antimony contract has been completed by June 30, 2026, with a disclosed or implied dollar value. Resolves NO if no physical delivery is confirmed by June 30, 2026, or if the contract is restructured to delay initial deliveries.

Resolution Source

UAMY SEC filings, press releases, or earnings calls

Source Trigger

DLA first delivery confirmation — validates contract execution capability

regulatory-readerREGULATORY_EXPOSUREHIGH
View UAMY Analysis

Full multi-lens equity analysis